The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

The Department of Transportation (DOT), in coordination with the river-administering agency, performs compliance reviews for qualifying properties. While Section 4(f) requires that the river-administering agency’s recommendations for minimizing harm are considered during the planning process, the authority to administer and make Section 4(f) approvals ultimately resides with the DOT. The river-administering agency’s concurrence on any DOT Section 4(f) compliance documents should clearly state that its concurrence is contingent upon a favorable final determination for the project under...

River access is evaluated in the land use planning process.  Specific access needs for public enjoyment, as well as any limitations, are determined in the river management plan.  In keeping with the requirements of the Wild & Scenic Rivers Act, “wild” rivers are generally inaccessible, except by trail (no roads); “scenic” rivers are accessible by road, which generally don’t parallel the river; and “recreational” rivers may have parallel or crossing road and railroad access.

Timber management activities on non-federal lands outside the corridor are guided by state and local authorities. The river manager may provide technical assistance and/or work with state/local governments to protect river values.

No, there is no statutory requirement that a CRMP be revisited in a specified timeframe. However, the federal wild and scenic river-administrator should periodically review monitoring information to determine if there is a need for change in existing direction to ensure values are protected and enhanced. Agency unit-wide plans that are revised following a CRMP-specific plan amendment will follow individual agency practices for plan revision. In some cases, this may include updating the CRMP during the agency unit-plan revision cycle.

No. However, all treatments must protect river values. Treatment methods that also include in-channel activity (e.g. dredging) are subject to review under Section 7(a) as water resources project.

Ideally one coordinated CRMP is developed with each wild and scenic river-administering agency documenting its respective decisions. In a few cases, separate plans may be required. However, even in this case, the planning process is conducted jointly to the greatest extent possible to ensure consistency of outstandingly remarkable values, classification, standards, and monitoring.

Yes. The Wild & Scenic Rivers Act directs other federal agencies to protect river values. It explicitly recognizes the regulatory roles of the Federal Energy Regulatory Commission and the Environmental Protection Agency in protecting wild and scenic rivers, and directs other federal departments and agencies that permit or assist in the construction of water resources projects to do likewise. The role of such federal agencies in water resources project construction may be through regulation, direct funding, or indirectly funding by providing federal assistance to others.

All...

Citizen stewards are increasingly important in protecting wild and scenic river values, often through river-specific or regional stewardship organizations. Individually, or through nonprofit entities, citizens help survey and monitor resource conditions, provide interpretive and education opportunities, contribute to restoration efforts, and support many other protection activities.

Agency officials are required to coordinate when their responsibilities relevant to wild and scenic rivers overlap.  Officials should determine the level of study to be conducted, who will lead the study, and, to the extent necessary and feasible, prepare a joint document for submission to Congress or congressional delegations.

Amending the lateral boundary of a designated river requires analysis and decision under the National Environmental Policy Act (NEPA). The environmental analysis process need not be complicated and may only require the proposed action and a no-action alternative. Amendment of a wild and scenic river boundary may also be timed with revision of the comprehensive river management plan and related decision under the NEPA. In either case, notice of the amended boundary should be published in the Federal Register and the legal description and maps forwarded to Congress and made...

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

Yes. While Congress specifies the termini of a designated river, in some instances congressional language may require interpretation. For example, a terminus described as “from the dam” could be interpreted as including the dam and dam-related facilities. However, to allow for continued dam maintenance, it may be appropriate to establish the boundary a very short distance below the dam or, through specific language, to exclude appurtenant facilities.

The river administrator is well advised to consider on-the-ground practicalities at the initial boundary setting stage, to the extent...

Once determined eligible, river segments are tentatively classified for study as either wild, scenic, or recreational based on the level of development of the shoreline, watercourse and access at the time of river is found eligible. If designated by Congress, the river’s enabling legislation generally specifies the classification.

Yes. There are four other principal agencies with authority on rivers, including wild and scenic rivers, in the United States. The EPA has authority to protect water quality; the Army Corps of Engineers (ACOE) has jurisdiction for water resources projects; the U.S. Coast Guard (USCG) has jurisdiction on inland navigable waters, vessel inspecting and licensing, safety and boating enforcement, aids to navigation, and permitting of bridges; and the Federal Energy Regulatory Commission (FERC) has authority to license the construction of hydroelectric projects.

No. The Wild & Scenic Rivers Act specifically prohibits the federal government from expending funds on Section 2(a)(ii) rivers, except to manage federal lands or to provide technical assistance to local managers.

Local government entities are encouraged by federal wild and scenic river-administering agencies to provide for the protection of wild and scenic river values in their land use plans, including the use of zoning and other land use measures. Their participation in development of the comprehensive river management plan (CRMP) in areas of mixed ownership is essential to ensure an enduring planning strategy that protects river values and respects the rights of landowners. In some cases, local governments have chosen to strengthen land-use requirements during a wild and scenic river study, in...

No restrictions to private lands may be applied under the Wild & Scenic Rivers Act. Comprehensive river management plans may establish goals for new construction consistent with classification. There is a wide range of uses compatible with these classifications so long as the overall values and character of the river corridor is maintained. Any effect on private lands would be through state or local zoning. Federal acquisition of lands or development rights would require landowner compensation.

Should the purchase of land become necessary, condemnation is typically a last resort and only used when:

  1. Land is clearly needed to protect resource values, or provide necessary access for public recreational use, and a purchase price cannot be agreed upon.

  2. Clear title to a property is needed, in which case condemnation is merely a legal procedure that has nothing to do with government/landowner differences.

Yes. Water may be secured through a variety of protection strategies, in the interim. Ultimately, the United States should secure a federal reserved water right in state court or the appropriate forum. Interim measures may include, but are not limited to: state instream flow programs, reservoir operation schedules, endangered species flow recommendations, conservation techniques, cooperative agreements, and water right purchases from willing sellers.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water...

The Interagency Guidelines interpret Section 10(a) of Wild & Scenic Rivers Act (the protect and enhance mandate) as “a non-degradation and enhancement policy for all designated river areas, regardless of classification. . . . Specific management strategies will vary according to classification but will always be designed to protect and enhance the values of the river area.” The overarching goal articulated in Section 10(a) is to protect existing high-quality conditions while improving conditions when unacceptable impacts are documented, thus leaving each river to future generations in...

Yes, per Sections 3(b) and 15(1) for rivers designated by Congress under Section 3(a), but not for rivers designated by the Secretary of the Interior under Section 2(a)(ii). For 2(a)(ii) rivers, states and/or local government set the boundaries, if any, for rivers in their systems; these rivers are not subject to Section 3(b) or the 320/640-acre limitation.

Rivers in Alaska outside of national parks and Elkhorn Creek in Oregon (640 acres per river mile) exceed the 320 acre average.

Through the various federal agencies’ land management planning processes and initiatives by the public, a significant number of rivers have been identified for study as potential additions to the National Wild & Scenic Rivers System. For example, the Nationwide Rivers Inventory (NRI), maintained by the National Park Service, has identified over 3,400 river segments as potential candidates for study and/or inclusion into the National System.

Once such a river segment has been found to be ineligible, the agency will manage the river and its corridor based on the underlying management direction in its programmatic plan and need no longer protect it as a potential wild and scenic river.

The requirement for a comprehensive river management plan (CRMP), does not apply to state-administered, federally designated rivers. Federal land managers are responsible for protecting river values in all agency planning and management actions for any portion of a 2(a)(ii) river that flows on federal lands. In some cases, the petitioning state has a requirement for a plan. The existence of a state or local plan to protect river values is one of the factors considered by the National Park Service in its review of the 2(a)(ii) nomination for the Secretary.

A range of projects are allowable to restore natural channel processes and habitat, including placement of limited rock and wood, native plantings to stabilize streambanks, and the removal or addition of fish barriers. Such projects are most likely to protect river values, including a river’s free-flowing condition, provided they: 

  1. Mimic the effects of naturally occurring events such as trees falling in and across the river (including the formation of wood jams), boulders tumbling in or moving down the river course, exposure of bedrock outcrops, bank sloughing or...

Agency land use or resource management plan records should include documentation of the eligibility criteria, inventory process, evaluation, and outcome. Agency field offices retain the administrative record and documents related to an assessment of the free-flowing condition and identification of outstandingly remarkable values.

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

WSR designation seeks to protect and enhance a river’s current natural condition and provide for public use consistent with retaining those values. Designation affords certain legal protection from adverse development, e.g., no new dams may be constructed, nor federally assisted water resource development projects allowed that are judged to have an adverse effect on designated river values. Where private lands are involved, the federal managing agency will work with local governments and owners to develop voluntary protective measures.

There are three instances when federal agencies assess eligibility: 1) at the request of Congress through specific authorized studies; 2) through their respective agency inventory and planning processes; or 3) during National Park Service evaluation of a Section 2(a)(ii) application by a state. River areas identified through the inventory phase are evaluated for their free-flowing condition and must possess at least one outstandingly remarkable value.

Boundaries are measured from the ordinary high water mark of the outermost stream channel. That is, boundaries will be measured from the outermost braid unless otherwise specified by Congress. This is typically considered during the suitability determination and in the development of the final river corridor boundary.

Wild and scenic river designation seeks to protect and enhance a river’s current condition. Generally, the classification of the river reflects the level of development at the time of designation, and future development levels must be compatible with such classification. Any proposed new developments on federal lands must be guided by land use and resource management objectives that are compatible with the river’s classification.

The economic impacts of implementing various alternatives should be addressed through the evaluation process to determine whether a river is a suitable addition to the National Wild & Scenic Rivers System or through the river management planning process, or a designated wild and scenic river. Economic issues, such as development and ecotourism, both inside and outside of potentially designated river corridors may be considered.

As of June 2022, some 226 river segments comprising 13,417 miles have been afforded protection in the National System.  These nationally recognized rivers comprise some of the nation’s greatest diversity of recreational, natural, and cultural resources, offering great scientific value and scenic beauty.  By comparison, more than 75,000 large dams across the country have modified at least 600,000 miles, or about 17% of America’s rivers (possibly more than 20% – figures are best estimates).

A variety of methodologies are used to determine instream flows necessary to protect flow-dependent outstandingly remarkable values for a specific wild and scenic river. Methodologies can range from staff/expert opinions (e.g., flows necessary for boating) to complicated hydraulic models (e.g., Instream Flow Incremental Methodology and Physical Habitat Simulation Models) used to simulate fish habitat requirements.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager...

Section 16(c) of the Wild & Scenic Rivers Act defines a scenic easement as follows:

“Scenic easement” means the right to control the use of land (including the air space above such land) within the authorized boundaries of a component of the wild and scenic river system, for the purpose of protecting the natural qualities of a designated wild, scenic, or recreational river area, but such control shall not affect, without the owner’s consent, any regular use exercised prior to the acquisition of the easement.

While the Wild & Scenic Rivers...

Federal lands within the boundaries of designated river areas (one-quarter mile—one-half mile for rivers in Alaska located outside national parks—from the bank on each side of the river) classified as wild are withdrawn from appropriation under the mining and mineral leasing laws by Sections 9(a) and 15(2) of the Wild & Scenic Rivers Act. Federal lands within the boundaries of designated river areas classified as scenic or recreational are not withdrawn under the Wild & Scenic Rivers Act from the mining and mineral leasing laws....

In the Wild & Scenic Rivers Act, river values identified include scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values. The Wild & Scenic Rivers Act does not further define outstandingly remarkable values. However, agency resource professionals have developed interpretive criteria for evaluating river values (unique, rare, or exemplary) based on professional judgment on a regional, physiographic, or geographic comparative basis. (Refer to The Wild & Scenic River Study Process (1999).)

The requirements specified for a CRMP in Section 3(d)(1) are most often developed through a separate-in-time planning process. This can result in either an amendment to the direction in the agency’s unit-wide plan o a stand-alone plan, depending on agency practices. For designated rivers that are separate NPS units, the CRMP is the General Management Plan (e.g., St. Croix National Scenic Riverway).

The Wild & Scenic Rivers Act requires that detailed boundaries portrayed on maps be established and submitted to Congress within one year of designation. Agencies may finalize boundaries through their respective land management planning process.

Pending the establishment of detailed river boundaries, the Wild & Scenic Rivers Act specifies that the interim boundary is one-quarter mile on each side of the river as measured from the ordinary high water mark.

Section 3(b) of the Wild & Scenic Rivers Act states:

The agency charged with the...

(*For some rivers, Congress has directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground circumstances and, therefore, are unlikely to require subsequent amendment.)

Yes. In a very few cases, the legislation designating a river erroneously describes a segment division and needs to be amended to fit on-the-ground circumstances. For example, the designating language for the Upper Rogue Wild & Scenic River...

Section 10(a) of the Wild and Scenic Rivers Wild & Scenic Rivers Act directs that:

Each component of the national wild and scenic rivers system shall be administered in such manner as to protect and enhance the values which caused it to be included in said system without, insofar as is consistent therewith, limiting other uses that do not substantially interfere with public use and enjoyment of these values.

In its technical report on managing wild and scenic rivers (Wild and Scenic River Management Responsibilities (2002)) the...

Yes, the federal government may seek to control use on adjacent lands under very limited circumstances. The Constitution gives the federal government certain limited powers to control uses on state-owned lands that affect adjacent federal property. These powers may be exercised through the Property Clause, which provides that, “Congress shall have the power to make all needful rules and regulations respecting the territory or the property belonging to the United States.”

The federal government may also regulate use and/or activities occurring on the surface waters...

River-administering agencies must evaluate proposed water resources projects under the appropriate standard of Section 7. The evaluative standard for projects located within a wild and scenic river corridor, Section 5(a) study area, or qualifying Section 2(a)(ii) application area is whether the project would have a “direct and adverse effect.” The evaluative standard for projects located downstream, upstream, or on a tributary to a wild and scenic river corridor or Section 5(a) study area is whether the project would “invade the area or unreasonably diminish” for designated wild and scenic...

Congress declared its intent to protect the water quality of rivers added to the National Wild & Scenic Rivers System in Section 1(b) of the Wild & Scenic Rivers Act. Congress further specified that the river-administering agencies cooperate with the EPA and state water pollution control agencies to eliminate or diminish water pollution (Section 12(c)).

The following summarizes the sections of the Wild & Scenic Rivers Act related to water resources (quality and quantity):

Section 1(b) of the Wild & Scenic Rivers Act establishes that the national policy of dam and other construction be complemented by a policy that would preserve other selected rivers or sections thereof “in their free-flowing condition to protect the water quality of such rivers and to fulfill other vital national conservation purposes.”

Section 10(a) states: “Each component of the national wild and scenic rivers system shall be administered in...

There are more appropriate and cost-effective ways to ensure resource conservation along wild and scenic rivers than using the Wild & Scenic Rivers Act’s condemnation authority. (Refer to Protecting Resource Values on Non-federal Lands (1996).)

Agencies may acquire properties using appropriated funds under the Land and Water Conservation Fund Act or other authorities. Owners are contacted in order to see if an exchange or voluntary purchase can be negotiated.

The Wild & Scenic Rivers Act states that rivers designated under Section 2(a)(ii) “shall be administered by the State or political subdivision thereof without expense to the United States other than for administration and management of federally owned lands.” The state is responsible for providing protection, except on federally administered lands and with respect to Section 7(a) determinations and securing a federal reserved water right under Section 13(c), both of which are made by a federal agency. The National Park Service provides ongoing technical assistance and partnership...

Generally, existing livestock grazing practices and related structures are not affected by designation. The Interagency Guidelines state that agricultural practices should be similar in nature and intensity to those present in the area at the time of designation, and that grazing may be compatible with all river classifications (wild, scenic or recreational). Grazing and other public uses may occur in a wild and scenic river corridor as long as the uses do not adversely impact or otherwise degrade the values for which a river was designated.