Eligibility findings are made as a part of a congressionally authorized study under Section 5(a), or pursuant to agency inventory and planning under Section 5(d)(1).  For Section 2(a)(ii) rivers, the National Park Service will make an eligibility determination under authority delegated by the Secretary of the Interior following application by the governor(s) for federal designation.

Maintenance of roads generally would not be affected. In consultation with landowners involved through coordinated management planning, every effort would be made to eliminate or reduce adverse impacts from any proposals for road improvement, realignment and/or new construction. If a proposed new road would have a negative impact on river values, the administering agency will work with the landowner(s) to mitigate the proposal. Should mitigation and/or consultation fail to reduce adverse impacts to an acceptable level, the administering agency could negotiate with the landowner to purchase...

Yes, but with many restrictions. It is important to note that condemnation is a tool that has been used only rarely on wild and scenic rivers. The objective of wild and scenic river designation is to protect and, as possible, enhance the values which caused the river to be designated. Should some proposed or actual use clearly threaten the values the river was designated to protect, the river managing agency would work with a landowner to explore ways to avert the threat through local zoning, state provisions, land exchanges, or purchases on a willing-seller/willing-buyer basis....

Section 16(b) of the Wild & Scenic Rivers Act, defines a “river” as “a flowing body of water . . . or portion, section, or tributary thereof. . . .”  “Free-flowing” is defined as “existing or flowing in natural condition without impoundment. . . .”  Therefore, any section of river with flowing water meets the technical definition of free flowing, even if impounded upstream.

Yes. Motorized access allowed prior to designation will, generally, be allowed post designation, subject to congressional intent and river management objectives. However, if motorized use adversely impacts a river’s water quality or outstandingly remarkable values, or if the use is not consistent with the river’s classification the route may be closed or regulated.

The continued legality of motorized use on land or water is best determined through the river management planning process, which considers factors such as impacts on river values, user demand for such motorized...

Section 16(b) of the Wild & Scenic Rivers Act defines a river as “a flowing body of water or estuary, or a section, portion, or tributary thereof, including rivers, streams, creeks, runs, kills, rills, and small lakes.”

The following summarizes the sections of the Wild & Scenic Rivers Act related to water resources (quality and quantity):

Section 1(b) of the Wild & Scenic Rivers Act establishes that the national policy of dam and other construction be complemented by a policy that would preserve other selected rivers or sections thereof “in their free-flowing condition to protect the water quality of such rivers and to fulfill other vital national conservation purposes.”

Section 10(a) states: “Each component of the national wild and scenic rivers system shall be administered in...

Section 8(a) of the Wild & Scenic Rivers Act withdraws public (federal) lands within the authorized boundary of a designated component from entry, sale, or other disposition under the public land laws of the United States.

Congress declared its intent to protect the water quality of rivers added to the National Wild & Scenic Rivers System in Section 1(b) of the Wild & Scenic Rivers Act. Congress further specified that the river-administering agencies cooperate with the EPA and state water pollution control agencies to eliminate or diminish water pollution (Section 12(c)).

The government typically provides technical assistance to find ways to alleviate or mitigate the actual or potential threat(s). Purchasing a partial right (easement) or the property in fee title is usually the last resort. If an easement is purchased, the owner would sell certain development rights and receive a payment, yet retain title to the land.

Yes. In some river study authorizations Congress has required the study agency to work with state and local governments and the public to develop a CRMP in concert with the study process to assist in determination of the river’s suitability. Such pre-designation CRMPs have, in some cases, been adopted in the legislation adding the river to the National Wild & Scenic Rivers System. In cases where Congress has not authorized a pre-designation CRMP, agencies have taken the initiative to develop elements of the CRMP in the study report (pre-designation).

Amending the lateral boundary of a designated river requires analysis and decision under the National Environmental Policy Act (NEPA). The environmental analysis process need not be complicated and may only require the proposed action and a no-action alternative. Amendment of a wild and scenic river boundary may also be timed with revision of the comprehensive river management plan and related decision under the NEPA. In either case, notice of the amended boundary should be published in the Federal Register and the legal description and maps forwarded to Congress and made...

The Wild & Scenic Rivers Act requires that detailed boundaries portrayed on maps be established and submitted to Congress within one year of designation. Agencies may finalize boundaries through their respective land management planning process.

Pending the establishment of detailed river boundaries, the Wild & Scenic Rivers Act specifies that the interim boundary is one-quarter mile on each side of the river as measured from the ordinary high water mark.

Section 3(b) of the Wild & Scenic Rivers Act states:

The agency charged with the...

Section 10(a) of the Wild and Scenic Rivers Wild & Scenic Rivers Act directs that:

Each component of the national wild and scenic rivers system shall be administered in such manner as to protect and enhance the values which caused it to be included in said system without, insofar as is consistent therewith, limiting other uses that do not substantially interfere with public use and enjoyment of these values.

In its technical report on managing wild and scenic rivers (Wild and Scenic River Management Responsibilities (2002)) the...

Easements on private lands acquired for the purposes of protecting wild and scenic rivers do not provide public access unless this right was specifically acquired from the private landowner. A trail or road easement by necessity would involve public use provisions. Any provisions for public use of private lands must be specifically purchased from the landowner.

The Wild & Scenic Rivers Act expressly prohibits the Federal Energy Regulatory Commission (FERC) from licensing the construction of a hydroelectric project or project works (e.g., facilities such as the powerhouse, access roads, transmission lines) under Part 1 of the Federal Power Act “on or directly affecting” a designated wild and scenic river. However, on the few rivers with a FERC-licensed hydroelectric project/project works within the river’s boundaries at the time of designation, existing operations may continue.

Relicensing of existing FERC-licensed hydroelectric...

In many cases, there may be no practical effect. However, laws like the Wilderness Act do allow certain activities in designated wilderness which may be incompatible on a wild and scenic river, e.g., water resource developments if authorized by the President. In addition, wild and scenic river designation prohibits federal participation in, or assistance to, water resource developments upstream or downstream of a designated river (potentially outside the wilderness area) which may adversely affect the designated river segment. Agencies are required by policy and law to evaluate potential...

Yes. Under Section 5(a) of the Wild & Scenic Rivers Act, the public is involved in the study of rivers authorized by Congress. The report associated with a congressionally authorized study addresses subjects such as current status of land ownership and use in the area; reasonably foreseeable potential uses of land and water which would be affected by designation; the federal agency to administer the river if designated; and the ability of, and estimated costs to, state and local agencies to participate in the administration of such rivers. The public and state, local and tribal...

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

Through the various federal agencies’ land management planning processes and initiatives by the public, a significant number of rivers have been identified for study as potential additions to the National Wild & Scenic Rivers System. For example, the Nationwide Rivers Inventory (NRI), maintained by the National Park Service, has identified over 3,400 river segments as potential candidates for study and/or inclusion into the National System.

There are more appropriate and cost-effective ways to ensure resource conservation along wild and scenic rivers than using the Wild & Scenic Rivers Act’s condemnation authority. (Refer to Protecting Resource Values on Non-federal Lands (1996).)

Agencies may acquire properties using appropriated funds under the Land and Water Conservation Fund Act or other authorities. Owners are contacted in order to see if an exchange or voluntary purchase can be negotiated.

No, not unless necessary to protect public safety, the river’s water quality, or other resource values. Recreational use of our nation’s rivers is increasing in both magnitude and extent, i.e., the types of recreational activities pursued and the technologies being used. Whether and how to restrict recreational use is a key issue in the planning process, which includes extensive local, regional, and national public involvement.

Generally, no. Any provisions for public use of private lands must be specifically included in the terms of the easement. Depending upon the terms and conditions of each easement, public access rights may or may not be involved. For example, a scenic easement may only involve the protection of narrowly defined visual qualities with no provisions for public use. A trail or road easement by necessity may involve public use provisions.

Yes.  The Nationwide Rivers Inventory lists potentially eligible rivers.  Federal agencies should make an eligibility determination for rivers on the Nationwide Rivers Inventory.

Section 4(f) refers to the original section within the United States Department of Transportation (DOT) Act of 1966 (49 U.S.C. Section 303(c); 23 U.S.C. Section 138). The DOT Act was enacted to ensure that transportation plans and programs include measures to maintain or enhance the natural beauty of publicly owned public parks, recreation areas, wildlife/waterfowl refuges, and historic sites of local, state, or national significance transversed by highways.

Yes.  The federal agency should consider a wide variety of internal and external sources from which to identify potentially eligible rivers.  These sources may include:  American Rivers’ “Outstanding Rivers List,” statewide river inventories/assessments, published guidebooks, etc.  The important point is to develop and apply standardized criteria through a documented evaluation process for potential wild and scenic rivers.

Yes. Congress has frequently added wild and scenic river status to rivers flowing through national parks, national wildlife refuges, and designated wilderness. Each designation recognizes distinct values for protection, and management objectives generally designed to not conflict. In some cases, wild and scenic river designations extend beyond the boundaries of other administrative or congressional area designations, thereby providing additional protection to the free-flowing condition and river values of the area. Section 10(b) of the Wild & Scenic Rivers Act addresses potential...

No.  The Interagency Wild & Scenic River Guidelines state, “There are no specific requirements concerning the length or the flow of an eligible river segment.  A river segment is of sufficient length if, when managed as a wild, scenic or recreational river area, the outstandingly remarkable values are protected.  Flows are sufficient if they sustain or complement the outstandingly remarkable values for which the river was designated.

Yes. To withdraw a scenic or recreational river segment, the managing agency must submit a separate public land order or notice of realty action.

As provided in Sections 4(a) and 5(c) of the Wild & Scenic Rivers Act, the following factors should be considered and, as appropriate, documented as a basis for the suitability determination for each river.

  1. Characteristics which do or do not make the area a worthy addition to the National Wild & Scenic Rivers System. These characteristics are described in the Wild & Scenic Rivers Act (see factors 2 through 7) and may include additional suitability factors (8 through 13).

  2. The current status of land ownership and use in the area.

  3. The...

Yes. Section 6(b) of the Wild & Scenic Rivers Act specifically prohibits the use of condemnation for fee title purchase of private lands if 50 percent or more of the acreage within the boundaries on both sides of the designated river is in public ownership (i.e., owned by the federal, state, or local government). In addition, Section 6(a)(1) of the Wild & Scenic Rivers Act prohibits acquiring more than 100 acres per river mile within the corridor, which equates to a stip of land about 400-feet wide along both sides of the river. Fee title condemnation is allowed to clear title or...

Yes. River-administering agencies have an affirmative duty to evaluate pre-existing uses on federal lands to determine whether such uses are protecting the values for which the wild and scenic river was designated. Grazing may continue when consistent with protecting river values. If grazing practices are determined to be inconsistent with wild and scenic river management objectives, then changes in grazing practices may be required.

Once such a river segment has been found to be ineligible, the agency will describe the basis for this finding in the study report and follow its internal procedures to transmit the report to the Congress in accordance with Section 7(b) of the Wild & Scenic Rivers Act.

Wild and scenic river designation does not change land ownership or grant new privileges to the public on private lands. If the riverbanks are in private ownership, the landowner continues to control their use after designation. Ownership of the bed and bank of a river may be affected by whether the river is determined navigable.

Yes.  Congress and the Secretary of the Interior have designated many river segments which are above or below dams that have regulated flows.

No. The river study, enabling legislation, and subsequent management planning process will consider how best to protect river values while recognizing private property rights.

Section 6(a)(1) of the Wild & Scenic Rivers Act states:

The Secretary of the Interior and the Secretary of Agriculture are each authorized to acquire lands and interests in land within the authorized boundaries of any component of the national wild and scenic rivers system designated in Section 3 of this act . . . but he shall not acquire fee title to an average of more than 100 acres per mile on both sides of the rivers.

The Wild & Scenic Rivers Act authorizes fee title acquisition to the equivalent of about a 400 foot wide strip of land...

No. The public’s right to float a particular river does not change with designation. Neither does designation give river users the right to use, occupy, or cross private property without permission.

Should the purchase of land become necessary, condemnation is typically a last resort and only used when:

  1. Land is clearly needed to protect resource values, or provide necessary access for public recreational use, and a purchase price cannot be agreed upon.

  2. Clear title to a property is needed, in which case condemnation is merely a legal procedure that has nothing to do with government/landowner differences.

There are a number of steps that federal agencies use in their evaluation process:

  • Assessment of free-flowing condition and resource values.
  • Finding of eligibility or ineligibility.
  • Inventoried or tentative classification based on the development of shoreline, watercourse, and access.
  • Establishment of tentative, preliminary, or proposed boundaries and/or river areas.
  • Establishment of protective management requirements for eligible rivers.

Wild and scenic river designation seeks to protect and enhance a river’s current condition. Generally, the classification of the river reflects the level of development at the time of designation, and future development levels must be compatible with such classification. Any proposed new developments on federal lands must be guided by land use and resource management objectives that are compatible with the river’s classification.

Boundaries are measured from the ordinary high water mark of the outermost stream channel. That is, boundaries will be measured from the outermost braid unless otherwise specified by Congress. This is typically considered during the suitability determination and in the development of the final river corridor boundary.

River segments may be tentatively classified for protective management purposes prior to a final suitability determination and/or congressional action.  This ensures that river values and characteristics are protected (subject to agency policies and standards) until the evaluation process and possible designation is completed.

Yes.  There are three classifications (wild, scenic and recreational) that may be applied to a particular river segment. Distinct segments along the designated reach may contain differing and non-overlapping classifications (wild, scenic, or recreational), e.g., a 100-mile wild and scenic river may be classified as wild for 50 miles, scenic for 30 miles, and recreational for 20 miles.

Timber management activities on federal lands within wild and scenic river corridors must be designed to help achieve land-management objectives consistent with the protection and enhancement of the values that caused the river to be added to the National Wild & Scenic Rivers System. Management direction needed to protect and enhance the river’s values is developed through the river planning process. Wild and scenic river designation is not likely to significantly affect timber management activities beyond existing measures to protect riparian zones, wetlands, and other resource values...

A river identified for study under Section 5(d)(1) is protected by each agency’s policy; i.e., the Wild & Scenic Rivers Act provides no statutory protections. To the extent of each agency’s authority, the river’s free-flowing condition, water quality, outstandingly remarkable values, and classification are protected. Prior to a suitability study, the inventoried classification is protected. If, as the result of a suitability study, a less restrictive classification is recommended for a river or portion thereof, the agency is obligated to protect this recommended classification.

Section 13(g) of the Wild & Scenic Rivers Act allows the granting of easements and rights-of-way within the boundaries of designated components in accordance with applicable laws, provided that the conditions attached to the grant are consistent with the purposes of the Wild & Scenic Rivers Act.

Any portion of a right-of-way project that includes federally assisted construction that may affect the river’s free-flowing condition—and is not automatically prohibited by the Wild & Scenic Rivers Act—is subject to an evaluation by the river-administering agency under Section...

There are three instances when federal agencies assess eligibility: 1) at the request of Congress through specific authorized studies; 2) through their respective agency inventory and planning processes; or 3) during National Park Service evaluation of a Section 2(a)(ii) application by a state. River areas identified through the inventory phase are evaluated for their free-flowing condition and must possess at least one outstandingly remarkable value.