There are a number of steps that federal agencies use in their evaluation process:

  • Assessment of free-flowing condition and resource values.
  • Finding of eligibility or ineligibility.
  • Inventoried or tentative classification based on the development of shoreline, watercourse, and access.
  • Establishment of tentative, preliminary, or proposed boundaries and/or river areas.
  • Establishment of protective management requirements for eligible rivers.

No. The United States determines the quantity necessary to protect flow-dependent outstandingly remarkable values.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

Yes. While Congress specifies the termini of a designated river, in some instances congressional language may require interpretation. For example, a terminus described as “from the dam” could be interpreted as including the dam and dam-related facilities. However, to allow for continued dam maintenance, it may be appropriate to establish the boundary a very short distance below the dam or, through specific language, to exclude appurtenant facilities.

The river administrator is well advised to consider on-the-ground practicalities at the initial boundary setting stage, to the extent...

Section 4(f) refers to the original section within the United States Department of Transportation (DOT) Act of 1966 (49 U.S.C. Section 303(c); 23 U.S.C. Section 138). The DOT Act was enacted to ensure that transportation plans and programs include measures to maintain or enhance the natural beauty of publicly owned public parks, recreation areas, wildlife/waterfowl refuges, and historic sites of local, state, or national significance transversed by highways.

Should the purchase of land become necessary, condemnation is typically a last resort and only used when:

  1. Land is clearly needed to protect resource values, or provide necessary access for public recreational use, and a purchase price cannot be agreed upon.

  2. Clear title to a property is needed, in which case condemnation is merely a legal procedure that has nothing to do with government/landowner differences.

It depends on whether the collecting activity is commercial or noncommercial in nature and subject to river-administering agency regulation. Mining under the 1872 mining law is a commercial and business activity tied to valid existing rights of claims and is regulated as such (36 CFR 228, 43 CFR 3809, 8365, et al).

Non-commercial mineral collecting for recreational purposes (e.g., hobby collecting, rock-hounding, gold panning, sluicing, or dredging) may be authorized by the Bureau of Land Management or the U.S. Forest Service depending on the amounts collected, size and scale of...

Subject to valid existing rights, rivers authorized for study under Section 5(a) of the Wild & Scenic Rivers Act are withdrawn under the mining laws while in study status; this withdrawal covers the bed and bank and federal lands situated within one-quarter mile of the bank on each side of the river. River study areas are not withdrawn from mineral leasing but are subject to conditions determined by the appropriate Secretary necessary to safeguard the area during the study period. However, the bed and bank and federal lands within two miles of the bank of each side of the rivers...

No. The Wild & Scenic Rivers Act does not limit the amount of land that may be acquired through purchase of easements, i.e., acquisition of partial rights, such as development rights.

The requirement for a comprehensive river management plan (CRMP), does not apply to state-administered, federally designated rivers. Federal land managers are responsible for protecting river values in all agency planning and management actions for any portion of a 2(a)(ii) river that flows on federal lands. In some cases, the petitioning state has a requirement for a plan. The existence of a state or local plan to protect river values is one of the factors considered by the National Park Service in its review of the 2(a)(ii) nomination for the Secretary.

Agency land use or resource management plan records should include documentation of the eligibility criteria, inventory process, evaluation, and outcome. Agency field offices retain the administrative record and documents related to an assessment of the free-flowing condition and identification of outstandingly remarkable values.

Wild and scenic river designation does not change land ownership or grant new privileges to the public on private lands. If the riverbanks are in private ownership, the landowner continues to control their use after designation. Ownership of the bed and bank of a river may be affected by whether the river is determined navigable.

Maintenance of roads generally would not be affected. In consultation with landowners involved through coordinated management planning, every effort would be made to eliminate or reduce adverse impacts from any proposals for road improvement, realignment and/or new construction. If a proposed new road would have a negative impact on river values, the administering agency will work with the landowner(s) to mitigate the proposal. Should mitigation and/or consultation fail to reduce adverse impacts to an acceptable level, the administering agency could negotiate with the landowner to purchase...

Federal lands within the boundaries of designated river areas (one-quarter mile—one-half mile for rivers in Alaska located outside national parks—from the bank on each side of the river) classified as wild are withdrawn from appropriation under the mining and mineral leasing laws by Sections 9(a) and 15(2) of the Wild & Scenic Rivers Act. Federal lands within the boundaries of designated river areas classified as scenic or recreational are not withdrawn under the Wild & Scenic Rivers Act from the mining and mineral leasing laws....

Section 6(a)(1) of the Wild & Scenic Rivers Act states:

The Secretary of the Interior and the Secretary of Agriculture are each authorized to acquire lands and interests in land within the authorized boundaries of any component of the national wild and scenic rivers system designated in Section 3 of this act . . . but he shall not acquire fee title to an average of more than 100 acres per mile on both sides of the rivers.

The Wild & Scenic Rivers Act authorizes fee title acquisition to the equivalent of about a 400 foot wide strip of land...

Yes. The ability of the owner to buy, sell, donate, or leave property to heirs is unaffected by the Wild & Scenic Rivers Act. Landowners who sell should inform the new owner of any easement transferred with the title.

A primary objective of wild and scenic river designation is to protect and enhance riparian area function and other river-related natural values. Specific actions to meet the objective are typically set forth in the management plan required for each river.

Regardless of the study agency’s eligibility and suitability findings, a Section 5(a) study river is protected by the conditions and restrictions specified in Sections 7(b), 8(b), 9(b), and 12(a) of the Wild & Scenic Rivers Act during the period of the study, plus up to three years after the required report is submitted to Congress. In other words, these protections are independent of the recommendation of the study, allowing for Congressional consideration.

A Section 5(d)(1) study river is protected to the extent of each study agency’s authority and not by the Wild & Scenic Rivers Act. Each agency’s policy is to protect eligible rivers and rivers determined suitable for designation for the life of the respective agency land use plan. A river determined not suitable for designation need no longer be protected as a potential addition to the National Wild & Scenic Rivers System once the study, with its related decision document, is completed.

Wild and scenic river study reports are prepared in three instances:

  1. When Congress authorizes a study pursuant to Section 5(a) of the Wild & Scenic Rivers Act.

  2. For eligible rivers that have also been determined suitable by a federal land management agency pursuant to Section 5(d)(1) of the Wild & Scenic Rivers Act, when the agency deems it appropriate to forward the recommendation.

  3. For state-nominated Section 2(a)(ii) rivers, the National Park Service prepares a report determining whether the candidate river meets the requirements of...

Once such a river has been found eligible, the federal study agency should, to the extent it is authorized under the Wild & Scenic Rivers Act and subject to valid existing rights, ensure the river and the surrounding area are protected as a potential wild and scenic river pending a suitability determination.

Section 13(g) of the Wild & Scenic Rivers Act allows the granting of easements and rights-of-way within the boundaries of designated components in accordance with applicable laws, provided that the conditions attached to the grant are consistent with the purposes of the Wild & Scenic Rivers Act.

Any portion of a right-of-way project that includes federally assisted construction that may affect the river’s free-flowing condition—and is not automatically prohibited by the Wild & Scenic Rivers Act—is subject to an evaluation by the river-administering agency under Section...

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

Section 8(a) of the Wild & Scenic Rivers Act withdraws public (federal) lands within the authorized boundary of a designated component from entry, sale, or other disposition under the public land laws of the United States.

(*For certain rivers, Congress directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground practicalities and, therefore, are unlikely to require subsequent amendment.)

Yes. While Congress specifies the segment divisions of a designated river, in some instances congressional language may require interpretation. For example, a segment division between a wild and scenic classification described as “from the bridge”...

Yes. Such projects may be constructed to protect and enhance fish and wildlife. In-channel structures (e.g., placement of large wood to replicate natural stream conditions) and in-channel activities (e.g., dredging to protect listed species) are acceptable, provided they do not have a direct and adverse effect on the values of the river (its free-flowing condition, water quality, and outstandingly remarkable values. Similarly, in-channel habitat projects may also be constructed below/above a designated river so long as they do not unreasonably diminish the scenic, recreational, and fish...

There are three instances when federal agencies assess eligibility: 1) at the request of Congress through specific authorized studies; 2) through their respective agency inventory and planning processes; or 3) during National Park Service evaluation of a Section 2(a)(ii) application by a state. River areas identified through the inventory phase are evaluated for their free-flowing condition and must possess at least one outstandingly remarkable value.

Eligibility findings are made as a part of a congressionally authorized study under Section 5(a), or pursuant to agency inventory and planning under Section 5(d)(1).  For Section 2(a)(ii) rivers, the National Park Service will make an eligibility determination under authority delegated by the Secretary of the Interior following application by the governor(s) for federal designation.

Rivers included in the National Wild & Scenic Rivers System by act of Congress (under Section 3(a) of the Wild & Scenic Rivers Act) are administered by one of four federal agencies: Bureau of Land Management (BLM), National Park Service (NPS), U.S. Forest Service (USFS), and/or U.S. Fish & Wildlife Service (FWS) as specified in the legislation. Rivers included in the National Wild & Scenic Rivers System at the request of a governor and designated by the Secretary of the Interior (under Section 2(a)(ii) of the Wild & Scenic Rivers Act) are administered by the respective...

Yes, per Sections 3(b) and 15(1) for rivers designated by Congress under Section 3(a), but not for rivers designated by the Secretary of the Interior under Section 2(a)(ii). For 2(a)(ii) rivers, states and/or local government set the boundaries, if any, for rivers in their systems; these rivers are not subject to Section 3(b) or the 320/640-acre limitation.

Benefits may include, but are not limited to, providing managers tools or mechanisms to protect free-flowing condition, i.e., protection of river values through the assessment of hydroelectric facilities or water resource development projects within the designated reach; protection and enhancement of water quality and outstandingly remarkable values; and, if a river’s management plan objective, promotion of economic development, tourism, or recreational use. Based on current limited studies, indications are that property values remain stable or increase on designated rivers. This is often...

Under Section 5(a), Congress directs that a study be conducted on identified river segments (usually within three years).  The designated federal agency conducts a study and subsequently reports its findings through the appropriate Secretary.  As a general rule, where joint agency jurisdictions are involved, the cooperating agencies coordinate their efforts prior to making recommendations or submitting reports.

Under Section 5(d)(1), federal agencies are directed to identify and evaluate potential additions to the National Wild & Scenic Rivers System through agency...

Section 10(a) of the Wild and Scenic Rivers Wild & Scenic Rivers Act directs that:

Each component of the national wild and scenic rivers system shall be administered in such manner as to protect and enhance the values which caused it to be included in said system without, insofar as is consistent therewith, limiting other uses that do not substantially interfere with public use and enjoyment of these values.

In its technical report on managing wild and scenic rivers (Wild and Scenic River Management Responsibilities (2002)) the...

A river authorized for study under Section 5(a) of the Wild & Scenic Rivers Act is subject to the conditions and restrictions specified in Sections 7(b), 8(b), 9(b), and 12(a) of the Act.

The river is protected for the duration of the study plus up to three years after the required report is submitted (along with the President’s recommendation) to Congress. Should Congress not act within the three-year time frame, the river is no longer afforded protection by the Wild & Scenic Rivers Act. In cases where a study has not been submitted to Congress, the statutory protections...

The Wild & Scenic Rivers Act expressly prohibits the Federal Energy Regulatory Commission (FERC) from licensing the construction of a hydroelectric project or project works (e.g., facilities such as the powerhouse, access roads, transmission lines) under Part 1 of the Federal Power Act “on or directly affecting” a designated wild and scenic river. However, on the few rivers with a FERC-licensed hydroelectric project/project works within the river’s boundaries at the time of designation, existing operations may continue.

Relicensing of existing FERC-licensed hydroelectric...

No. However, all treatments must protect river values. Treatment methods that also include in-channel activity (e.g. dredging) are subject to review under Section 7(a) as water resources project.

Prior to completion of the CRMP, proposed projects and new decisions (e.g., issuance of a special-use permit) on federal lands are evaluated by the wild and scenic river-administering agency to ensure they protect and, to the extent possible, enhance river values (free-flowing condition, water quality and outstandingly remarkable values). The necessary evaluation framework is a detailed description of the existing conditions of these values at the time of designation. Absent this information it may not be possible to evaluate the effects of an activity relative to the non-degradation and...

Protective management of federal lands in the river area begins at the time the river segment(s) has been found eligible.  The free-flowing condition, identified outstandingly remarkable values, and classification are protected to the extent authorized under law and subject to valid existing rights.  Affording adequate protection requires sound resource management decisions based on National Environmental Policy Act (NEPA) analysis.  Protective management should be initiated by the administering agency as soon as eligibility is determined.  Specific management...

The river-administering agency must take the actions necessary to remedy adverse impacts and/or show measurable progress in addressing identified adverse effects. The Wild & Scenic Rivers Act gives river-administering agencies authority to adjust or eliminate livestock grazing, or any other commercial use, if doing so is necessary to meet the protection and enhancement standard.

Agency officials are required to coordinate when their responsibilities relevant to wild and scenic rivers overlap.  Officials should determine the level of study to be conducted, who will lead the study, and, to the extent necessary and feasible, prepare a joint document for submission to Congress or congressional delegations.

(*For some rivers, Congress has directed the river-administering agency in Section 3(b) to determine which classes “best fit the river or its various segments.”  These administratively segmented rivers should reflect on-the-ground circumstances and, therefore, are unlikely to require subsequent amendment.)

Yes. In a very few cases, the legislation designating a river erroneously describes a segment division and needs to be amended to fit on-the-ground circumstances. For example, the designating language for the Upper Rogue Wild & Scenic River...